Carolina Street Extension Complete

Print
Press Enter to show all options, press Tab go to next option

Project Update  

The road project was completed in June 2019. The Town of Morrisville's Public Works staff completed the roundabout landscaping work in Nov. 2019. Duke Energy completed the street light installation on Carolina St. Extension and on Foxglove Drive Extension in Nov. 2019. 

Overview 

This project is a key piece of the Town Center Core Demonstration project, which is currently in development. The proposed Town Center Core Demonstration project site includes the area between Town Hall Drive (west) and future Foxglove Drive (east), and Jeremiah Street (north) to Carolina Street extension (south). The demonstration project site concept includes a new Wake County Library, apartments, retail space and parking. The Wake County Library began in late 2018 and is scheduled to be open in the summer of 2020. 

Major Project Milestones:

  • Spring 2018: Project Contract Awarded
  • Summer 2018: Start of Construction
  • Spring 2019: Project Completed; Open June 1

Frequently Asked Questions:

How long did this project take?

Construction started in Summer 2018 and finished in Spring 2019, ahead of schedule and under budget.

I'm not familiar with roundabouts. How do I know where to drive?

Here's a video to help navigate roundabout traffic:

Morrisville Contact:

Vinod Korategere
Capital Project Manager
919-463-6147
Email Vinod