Street Repair Projects

The Town of Morrisville hires a private engineering firm to perform a Pavement Condition Survey of all 49 miles of Town-owned streets. The Pavement Condition Survey (PCS) process involves categorizing and quantifying each type of pavement defect and determining the Pavement Condition Rating (PCR) for the road. The PCS is performed every two years to keep the information current.

Each year the Public Works Department determines roads in Town to be repaired based on a number of criteria, such as PCR, severity of defects, age of roadway, road classification, traffic volume, and available funding.

 

Public Works Current Projects

FY17 Street Maintenance Paving Project

TOWN OF MORRISVILLE

Fiscal Year 2017 Paving Project

Bids shall be received on or before October 5, 2016


In process:

There are no street maintenance paving projects in process at this time.

Completed:

Weston Estates - Streets List Attached - Finished 4/4/2016 - Striping is continuing through the end of 4/8/2016.
Summary of Work: Fred Smith Company is finishing work on the below streets in Weston Estates:

Asphalt milling, sidewalk repair, patching and a 2" overlay is expected to be completed the first of April, 2016. Please continue to check the site for updates on expected delays and other pertinent information. 

* Arrowstone Court
* Bailey Ridge Drive
* Bending Branch Court
* Briery Branch Court
* Brooktree Court
* Bruington Court
* Delaplane Court
* Glenspring Way
* Guymon Court
* Kalvesta Drive
* Keybridge Drive
* Rapidan Court
* Tarkington Court
* Weston Estates Way

Actual Construction Cost:  $542,200.65
Actual Construction Schedule: February 16, 2016 - Approximately April 1st - weather permitting


Treybrooke Drive - completed as of 4/4/2016 - Striping is continuing through the end of 4/8/2016.
Summary of Work: Fred Smith Company is starting work on Treybrooke Drive during the week of March 28th, 2016 starting concrete repair work on curbs and sidewalks. The repairs are estimated to complete April 1st, 2016, weather permitting. 

Page Street - completed as of 4/4/2016 - Striping is continuing through the end of 4/8/2016.
Summary of Work: Fred Smith Company is starting work on Page Street during the week of April 4th starting concrete repair work on curbs and sidewalks. The repairs are estimated to complete April 8th, 2016, weather permitting. 

Actual Construction Cost for both Treybrooke Drive and Page Street:  $185,852.00
 


Carpenter Park
Summary of Work:  Ruston Paving will be working on the below streets in Carpenter Park:

*Waldron Court
*Airtech Drive
*Millet Drive
*Kudrow Lane
*Lodgin Court
*Rama Court

Asphalt milling, patching and a 2" overlay is expected to start May 10th.

Cost: $294,330.00
Completed as of June 2, 2016
_____________________________________________________

Summary of Work: Contractor TBD, Slater Road and Copley Parkway

Full depth asphalt patching and a 2" overlay is expected to be completed by the beginning of June, 2016. Please continue to check the site for updates on expected delays and other pertinent information. 

Cost $94,780.00
Completed as of June 2, 2016
_____________________________________________________

Summary of Work: Striping project/Pavement marking on various Town roads. Arrowline Pavement Markings will begin mid-April and is expected to complete June, 2016.

Actual Cost Construction: $16,401.40
Actual Construction Schedule: Mid April, 2016 - June, 2016 
Completed June 2, 2016