Morrisville-Carpenter Road Improvements Project
Overview:
The Town recently began engineering and design work on improvements to Morrisville-Carpenter Road between Page Street and Davis Drive.  These improvements will include widening the road to four lanes, adding curb-and-gutter and sidewalk, and replacing the culverts at Indian Creek.  This project is a follow-up to a joint NCDOT/Town of Morrisville project completed in 2015 to widen Morrisville-Carpenter Road between Grace Park and the Ridgemont neighborhood and make improvements to the Davis Drive intersection.  The 2015 project also installed two pedestrian crossings with pedestrian-activated flashing beacons at the Grace Park/Morrisville Market Greenway crossing and at the Savannah neighborhood.      

The current engineering and design work on the improvements project is expected to be completed by 2017.  The Town was awarded construction funding from CAMPO in February 2017.    
 
Schedule:
  • January 2016 - Engineering and Design Work begins
  • February 2017-December 2017 - Right-of-Way Acquisition
  • Summer 2017 - Completion of Engineering and Design
  • Spring 2018-Summer 2019 - Construction
 

 Other Facts:

  • Estimated Total Project Cost (including engineering, design, permitting, ROW acquisition and construction): $11M   
Related Links/Documents:
                                       
Morrisville Contact:

Rich Cappola, P.E.
Town Engineer
(919) 463-6193
Email Rich

Benjamin Howell, AICP, CZO
Long Range Planning Manager
(919) 463-6927
Email Benjamin

 
Updated 3/8/2017